HEARTH PRODUCTS
KITS AND ACCESSORIES
FORCED AIR BLOWER KIT
FAB-1100
P/N 903249
REV. E 11/2004
INSTALLATION INSTRUCTIONS FOR BLOWER KIT
MODEL FAB-1100
GENERAL INFORMATION
Magnets
The FAB-1100 forced air blower kit consists of a 105 CFM dual
blower assembly.
Blower
in Position
The blower supplies air delivery at 105 CFM at 0" H2O static pressure,
90 CFM at 0.2" H2O static pressure. The maximum operating static
pressure is 0.38" H2O.
Magnets
The FAB-1100 has been tested and certified by CSA.
Always check local building codes. The installation must comply with
local regulations as well as the National Electric Code.
Make Entry where No Obstructions are Present.
Failure to follow these instructions could cause a fireplace malfunc-
tion resulting in possible injury and/or property damage.
Figure 1
PLEASE RETAIN THESE INSTRUCTIONS FOR FUTURE REFERENCE.
PRELIMINARY INSPECTION
Outlet
Plenums
Remove the blower kit from the carton and check for any damage.
Check inventory: blower assembly, sleeved power cord and installa-
tion instructions.
INSTALLING THE BLOWER
Step 1. In most appliances the FAB-1100 blower is simply posi-
tioned against the appliance back wall, with the magnets engaging
the sheetmetal rear wall to secure the blower in place. Generally
access to this location is gained by the opening (or removal) of the
appliance lower compartment door of louvers Figure 1.
FAB-1100
Blower
Blower
Base
Figure 2
Step 2. The blower is properly positioned when it is centered against
the appliance rear wall with the outlet plenums pointed upwards
(Figure 2 ). Ensure that the blower base is firmly seated on the
appliance base. Ensure that the blower is positioned against the
appliance back wall. Some appliances are fitted with a blower shield
preventing access to the back wall of the appliance. In this case
remove the shield, place the blower, complete its installation, then
replace the shield.
Note: The FAB-1100 may also be used with the PureHeat appliance and
the CGI-BAY and GI-3821 gas inserts. For use with the PureHeat and
CGI-BAY appliances follow the instructions in their installation docu-
ments and those found in the PHEXK and CBEK kits respectively. The
FAB-1100 is installed in the GI-3821 in accordance with instructions
provided with that appliance.
Step 3. Route the blower sleeved power cord to a switched, standard
grounded three pronged outlet mounted on the appliance internal "J"
box cover plate prewired at the time of appliance installation (see page
2 of this document, Figure 3 ). Ensure power cord minimizes contact
with hot appliance surfaces. Operate the FAB-1100 from the switch
controlling power to the appliance junction box.
NOTE: DIAGRAMS & ILLUSTRATIONS NOT TO SCALE.
|